20th July, 2017

TB Ramsden Steam Decentralisation Complete!

Ellie Lee

MCL Energy commercial team has recently completed the £60k decentralisation scheme at our long standing steam customer - TB Ramsden in Guiseley. MCL Energy have supported the coal fired boiler for a decade, but changes in their production process meant steam was no longer required. A solution to fully decentralise the existing site steam heating systems was agreed. The Scheme included full site natural gas infrastructure in stainless steel crimped pipe and fittings, supply and installation of 7 no warm air heaters in the range 50-140kW and independent area controls. Adrian Durose, Andy Jenkinson, Chris Wilson and Calvin Brown all contributed to the successful project with annual savings projected to be around £70,000. Thus providing an extremely impressive payback of less than 1 year!